What happened

Landlord applied for an order to terminate the tenancy and evict the Tenant due to failure to pay rent. The Tenant vacated the rental unit on August 31, 2021, prior to the hearing date.

The ruling

The tenancy is terminated effective August 31, 2021, the date the Tenant vacated the rental unit. The Tenant is ordered to pay $4,111.48 to the Landlord, which includes rent arrears, compensation, and the cost of filing the application, less the rent deposit and interest owed on the deposit.