What happened
Landlord applied for an order to terminate the tenancy and evict Tenants due to substantial interference and damage to the rental unit. The Landlord claimed the Tenants caused a flood by misusing the washing machine.
The ruling
The Landlord's application is granted. The tenancy is terminated effective August 31, 2024. The Tenant must pay the Landlord $12,939.34, which includes the cost of repairs and the application fee, minus the rent deposit and interest. If the Tenant does not pay by August 31, 2024, they will owe interest starting September 1, 2024.